2000
2000:
2001-2002:
2001:
2001:
2001:
2001:
2001:
2001:
2001-03:
2002:
2002:
2002:
2002:
2003:
|
Thorburn Spawning Channel constructed near Piedra
as first Kings River Fisheries Management Program
project.
Several Kings River fishery habitat improvement projects
undertaken.
Energy crisis prompts KRCD to take new look at Dinkey
Creek, Rodgers Crossing projects but both projects
are ultimately placed back on the shelf.
KRCD begins study of public power ownership.
Corps study finds federal interest in Pine Flat multi-level
intake structure.
KRWA, Metropolitan Water District of Southern California
begin studies of possible joint floodwater utilization
projects.
KRCD commemorates 50th anniversary.
KRCD begins studies on how to increase availability,
reliability and affordability of electrical energy
within the Valley.
Corps of Engineers constructs Turbine Bypass at Pine
Flat Dam.
KRWA begins installing telemetry at key locations
to aid in water management.
KRWA commemorates 75th anniversary.
KRWA and KRCD lead organization of Southern San Joaquin
Water Quality Coalition.
KRCD reaches agreement with state DWR to construct
two gas-fired peaker power generating
plants.
Pine Flat Dam Turbine Bypass System is completed and
dedicated.
|